- 100 Site
- 110 Footing
- 120 Slab
- 121 Sidewalk and Driveway
- 130 Footing/Slab (Mono)
- 150 Lintel
- 160 Tie Beam
- 170 Down pour
- 180 Masonry wall reinforcing
- 188 Window/Door installation
- 189 Sheathing
- 190 Framing
- 191 Fire rated assembly
- 192 Fire wall
- 210 Insulation
- 250 Fences
- 260 Pool Barrier/Safety Device
- 270 Landscaping final
- 279 Dry-In/Roof flashing
- 280 Roof final
- 290 Final
- 300 Use permit
- 310 Demolition inspection
- 320 Move
- 330 Relocate
- 340 Fire damage
- 350 Pool steel & ground
- 360 Mobile home tie-down
- 370 Tank corrosion & anchorage
- 380 Tank pressure
- 390 Tank gasoline piping pressure
|